Road Upgrade Works

1 April 2022

Mt Crosby Road Upgrades

Road upgrade and improvement works are to be carried out at Mt Crosby Road and Warrego Highway between Tuesday 4th October and Thursday 3rd November.

These roads have been identified for upgrades as part of the MacIntyre Wind Farm Project in Karara and Warwick. The roads will undergo upgrades to improve the intersections and establish an accessway for the transportation of larger project components.

Works will be undertaken between 8pm to 5am, Sunday to Thursday. Traffic management staff and signage will be in place as required during work hours. Some works being undertaken may occur outside of normal work hours, however the timing will be phased to ensure safety and access for all road users.

THE OVERVIEW OF THE PUBLIC ROAD UPGRADES INCLUDE:

• Relocating existing road signs
• Relocating existing light poles
• Replace existing guardrails
• Temporary removal of existing apron slab

Please see the map on this page.



River Road Roundabout Upgrades

Road upgrade and improvement works are to be carried out at River Road and Ashburn Road roundabout, Dinmore between Monday 17th October 22 and Friday 28th October 22.

These roads have been identified for upgrades as part of the MacIntyre Wind Farm Project in Karara and Warwick. The roads will undergo upgrades to improve the intersections and establish an accessway for the transportation of larger project components.

Works will be undertaken between 8pm to 5am, Sunday to Thursday. Traffic management staff and signage will be in place as required during work hours. Some works being undertaken may occur outside of normal work hours, however the timing will be phased to ensure safety and access for all road users.

THE OVERVIEW OF THE PUBLIC ROAD UPGRADES INCLUDE:

  • Relocating existing road signs
  • Relocating existing light poles
  • Replace existing guardrails
  • Establish tree protection zone as per AS4970-2009
  • Temporary removal of existing apron slab
  • Vacuum excavate and clean sever tree roots at furthest possible point from tree
  • Provide a new C.I. subsoil drain cleanout


Please see the map on this page.



For any questions about these works, please call: 1800 283 550 or email: macintyre@acciona.com